Finishes within a SS shall comply with the following:

a. The walls and the ceiling slab shall be cast with a smooth concrete finish.:

b. The walls and ceiling slab may be finished with a skim coat of not thicker than 2mm.

c. No plastering or tiling shall be permitted on the walls and ceiling slab.

d. Floor tiles or floor finishes, which are laid on wet cement mortar, are permitted.

e. Skirting tiles laid on wet cement mortar are permitted up to a maximum 100mm high above the FFL.